Sri Ramanuja Sahasrabdi Celebrations have gathered momentum. The whole atmosphere is buzzing with feverish anticipation on when the Statue of Equality – vigraham of great acharya Sri Ramanujacharya will appear in JIVA campus.

The Stone work, castings and polishing work, onsite erection of beams and elephants is going on full swing. The casting of 11th level has been completed out of 17 levels i.e., out of 34 mtrs the casting has been completed upto 22 mtrs. The 6th shipment is ready for dispatch. The dispatch clearance has been given. Fabrication of dynamic fountain and its mechanism is in progress.

RR.Engineering has completed erection of 20 out of 33 columns. 122 beams out of 244 beams erection has been completed raising up to the height of 10 meters level. 6 Columns assemblies and 17 beams reached the site. 3 columns are under fabrication and 5 columns are under marking out of 12 columns.

Finishing Touches on Bhadravedi Temple Complex Exterior work has been started at the site. Until now 16 truckloads of material have been received at site.

For Regular Updates on Statue of Equality, you can connect with us on Facebook 

 

The post Sixth Shipment of Statue of Equality On The Way!!! appeared first on Chinnajeeyar.

Source: Varija News